Cisco Secure Connect - [Planned Maintenance] Data Center, Europe(Milan) - From 2026-04-18 00:00 UTC to 2026-04-19 04:00 UTC

Scheduled Maintenance Report for Cloud Security Service Status

Completed

The scheduled maintenance has been completed.
Posted Apr 19, 2026 - 04:00 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 18, 2026 - 00:00 UTC

Update

The scheduled maintenance window has been revised.

Date & Time: April 18, 2026, 00:00 UTC to April 19, 2026, 04:00 UTC

Please note the updated schedule. Further updates will be provided if necessary.
Posted Apr 02, 2026 - 17:46 UTC

Scheduled

Cisco is committed to providing you with a secure and reliable experience. To ensure our Cisco Secure Connect platform continues to meet your needs, we will be performing maintenance.

Maintenance Details :
We will be performing upgrade maintenance on the data center component in the eu-south-1 (Milan) region.

Date and Time: April 18th, 2026, 00:00 UTC to April 19th, 2026, 04:00 UTC

Impact:
Remote Access VPN customers will be administratively disconnected from eu-south-1. They must reconnect manually, but will be automatically redirected to an alternate site. They may receive a certificate error if they are not using the "Auto Select" VPN option.

Data Centers
Europe (Milan) – eu-south-1

We’re Here to Help
If you have any questions or need assistance, please contact our support team.Thank you for your understanding and support.
Posted Mar 24, 2026 - 20:40 UTC
This scheduled maintenance affected: Secure Connect Europe (Data Center).